A garage conversion ADU in Prosper, TX typically runs $45,000 to $130,000 and takes 8 to 16 weeks from permit to final inspection, depending on whether you keep the existing slab and walls or move plumbing and structure. You keep the exterior footprint and gain a self-contained living space – with its own entry, kitchenette and bath – under a roof you already own. Call (844) 560-0925 for a free on-site estimate and a written line-item quote.

How We Turn a Prosper Garage Into a Living Space, Stage by Stage

The job follows a fixed sequence. Here’s what actually happens, and what you’ll be deciding along the way.
Stage 1: Site review and permit package (week 1)
We measure the garage, check how the existing slab handles water, and confirm ceiling height, door clearances and where the utilities enter. From those measurements we draft the layout and submit for a Prosper permit. You decide the floor plan here – studio, one-bedroom, or separate bedroom and bath – and this decision drives everything downstream.
Stage 2: Demo and shell prep (weeks 1 – 2)
The overhead garage door comes off, the opening gets framed and closed with a window wall or a framed exterior wall, and the old slab is patched, leveled or sleeded where it won’t take finish flooring. If the original apron slopes toward the street, we build the floor up to a level plane. You pick the new exterior entry here: side door versus a front-facing entrance.
Stage 3: Rough-in – plumbing, electrical, HVAC (weeks 2 – 4)
This is where the budget moves. Trenching the existing slab for a bath adds drainage and supply runs, so with the bath placed back-to-back on a wall, the run stays short. Electrical adds a dedicated panel or subpanel, GFCI protection, and lighting layout. HVAC is either a mini-split or a ducted tie-in to the main house. You decide bath placement, appliance locations, and the heating setup at this stage because it’s all in the same rough-in.
Stage 4: Insulation, drywall and finish-out (weeks 4 – 10)
Walls get insulated to code, drywall goes up, then finishes: flooring, kitchenette cabinets and counter, bath fixtures, paint and trim. We ask for your material selections – flooring type, cabinet grade, fixture finishes – at the start of this stage so deliveries land on time. A converted garage needs a solid thermal envelope; we don’t treat the insulated walls as optional on this house.
Stage 5: Final inspections and handover (weeks 10 – 16)
Framing, electrical, plumbing, mechanical and final inspections run through the city. We walk the finished space with you, confirm the smoke and CO alarms, the egress window, and the separation between the new unit and the main house, then hand you the documentation. Any punch items get fixed before we’re done.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Options You’ll Choose Between
- Modular pre-built shell (Dvele, Boxabl) versus site-built: modular shortens the exterior construction phase but locks in the floor plan and adds delivery and set costs, so it works best on a clean slab and simple layout. Site-built gives you full control over the floor plan and a smoother finish.
- Mini-split versus ducted HVAC: a mini-split handles a garage conversion well and keeps ductwork out of a low ceiling, while a ducted system ties into the existing unit but needs headroom for the duct chase.
- Tank water heater versus tankless: tankless saves closet space in a compact unit, but it needs a gas line or dedicated electrical circuit and the venting path, so factor the rough-in cost.
- LVP versus tile flooring: luxury vinyl plank is the value pick over a converted slab and handles moisture swings, while tile costs more and stays put.
- Kitchenette versus full kitchen: a compact counter, sink and two-burner cooktop keeps the utility load low; the full kitchen pushes the budget toward the high end.
- Egress window and entry door: both are required for a legal living space and affect the layout, so plan for them before framing.
What Garage Conversion ADU Costs in Prosper, TX
Plan on $45,000 to $130,000 for the job. The number is shaped by these variables:

- Size and finish grade: a studio conversion lands near the low end; a one-bedroom with a full bath and upgraded finishes pushes toward the top.
- Plumbing location: keeping the bath against an exterior wall close to the main line saves thousands in slab trenching and re-pouring. A bath end of the garage can add a long run.
- Structural changes: new headers, ceiling height changes and door re-work add framing and engineering.
- Electrical service: a subpanel and full kitchenette need a heavier load and an electrician’s panel work.
- Permit and inspection scope: a smaller conversion under the existing footprint has a narrower permit scope than one that pushes into the setback or adds a new utility trench.
Your written estimate covers framing, insulation, drywall, flooring, electrical, plumbing, HVAC and permit filings in a line-item format – the number you see is the number you pay, with no change orders. What typically isn’t included: the finish-grade appliances you supply, landscaping around the new entry, and anything that shows up beyond the scope if we uncover something unexpected. Your free on-site estimate gives you the real number for your garage.
See the difference
Before
After
Before
After
Before
AfterWhat Prosper Homes Specifically Do to This Job
Prosper is one of the fastest-growing exurban boomtowns in North Texas, and it shows. Most of the garages we convert in Prosper sit inside homes built within the last decade in the master-planned subdivisions spreading across former Blackland Prairie farmland, so we’re working on recent builds to current code, not patching aging structures. That cuts both ways. The slab is newer and often post-tension, which means we don’t cut into it casually, and the house is still under warranty, so work needs to respect that warranty. The expansive clay soil under Prosper is the other local reality: it swells and shrinks with the wet-dry cycle. A wet spring followed by a dry summer moves foundations and slabs in houses only a few years old, so when the garage slab has shifted, we assess and pier before finishing the floor. Upgrading the garage to living space also means a final inspection – and in Prosper new-build subdivisions, the HOA architectural review runs in parallel, so get that approval early. Local climatic pressure is real for this work. Our Prosper service area page covers the surrounding streets.
Serving Prosper, TX – Our Local Coverage Area
We serve Prosper and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked Questions – Garage Conversion ADU in Prosper

Most conversions take 8 to 16 weeks from permit to final inspection, with the permit itself adding a couple of weeks at the front. Plumbing and electrical changes inside the slab are the biggest drivers of timeline. Call (844) 560-0925 to schedule a free estimate and get a schedule dated to your job.
Yes. Converting a garage to living space is a change of use that requires a permit and inspections in Prosper, and the HOA architectural review may run alongside it. We handle the permit filings and coordinate the inspections. Call (844) 560-0925 for an estimate that includes the permit scope.
Often yes. Keeping the bath and kitchenette on the existing slab near the main utility lines avoids trenching and structural work, which keeps the job closer to $45,000. Moving the bath to the far end of the garage is what pushes it toward $130,000. Call (844) 560-0925 and we’ll walk your garage and tell you which side of that line it sits on.
The range runs $45,000 to $130,000, with material grade, plumbing location, structural changes and permit scope driving the number. A studio at the low end, a full one-bedroom with upgraded finishes at the high end. Call (844) 560-0925 – estimates are free and line-item.
Yes. Every garage conversion ADU we build is covered by our 730-Day Done Right Promise: if it isn’t done right, we make it right. That’s one of the longest workmanship guarantees in the residential construction space. Call (844) 560-0925 to start the estimate.
Get a Free Estimate on Your Prosper Garage Conversion
If you want real numbers for your garage, call (844) 560-0925. We schedule a free on-site visit, measure the space, review the slab and utilities, and give you a written, line-item estimate with the permit scope spelled out. Our technicians have up to 12 years of experience, and a live person answers the phone. The garage can become living space – let’s price it properly.
Written by the team at Groundwork Construction Co.