Garage Conversion ADU in Carrollton, TX: what it takes and what it costs
A Garage Conversion ADU in Carrollton usually runs $45,000 – $130,000 and takes about 3 to 5 months from first demo to final inspection, depending on whether you’re adding a bathroom and kitchenette or keeping it simple. The work converts an existing attached or detached garage into a legal, permitted living space: new framing and insulation, a raised floor over the slab, plumbing and electrical rough-in, HVAC, finishes, and the city inspections that make it count as habitable square footage. Call (844) 560-0925 and we’ll walk your garage and give you a real number.

How a garage conversion actually goes, stage by stage

Most homeowners picture a garage conversion as one big blur. It isn’t. It’s a sequence, and knowing what happens when tells you what you’ll be deciding and when.
- Days 1 – 5: demo and assessment. We pull the garage door and its tracks, remove any shelving or old storage build-outs, and open the slab and walls to see what we’re working with. This is where we confirm the slab condition and check the original cast-iron drain line if there’s a floor drain. You decide here whether to keep the existing side-entry door as your ADU entrance or frame a new one.
- Week 1 – 2: framing and the floor build-up. A garage slab sits below the house floor and has no vapor barrier built for living space. We frame the new walls, build up a raised subfloor with insulation and a moisture barrier, and rough in the window and door openings. You’ll pick window style and exterior door at this point.
- Week 2 – 4: plumbing and electrical rough-in. If you’re adding a bathroom or kitchenette, this is where the drain, water, and vent lines go in, and where the panel gets a sub-panel or circuit additions. Inspections happen before anything gets covered. You decide fixture locations now, because moving a drain later means breaking concrete.
- Week 4 – 7: HVAC, insulation, and drywall. A garage was never conditioned, so we add ductwork or a ductless mini-split, seal and insulate the envelope, then hang, tape, and texture the drywall. You pick the HVAC approach here; the trade-off is cost versus how evenly the space heats and cools.
- Week 7 – 12 and beyond: finishes and final inspection. Flooring, trim, paint, fixtures, the kitchenette, and the bathroom tile. Then the final building inspection that lets the space legally count as living area. You make most of your finish selections during this stretch, and the schedule depends on how fast those land.
Part of a full Home Additions & ADU in Carrollton plan, a garage conversion is often the least disruptive way to add square footage because you’re not pouring a new foundation or tying into the roofline.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The choices you’ll make, and the honest trade-offs
Every garage conversion comes down to a handful of decisions that swing both the price and how the finished space lives. Here’s what actually gets chosen:
- Bathroom: full, half, or none. A full bath with a shower is what makes the unit rentable or usable for family, but it’s the single biggest plumbing driver. A half bath (toilet and sink) saves money and concrete work but limits who can live there. Skipping plumbing entirely is the cheapest path and the least flexible.
- Kitchenette: wet bar or real cooking. A sink, mini-fridge, and counter suits a guest suite or home office. A full range and vent hood means a heavier electrical load and more venting, and it changes the permit scope.
- Flooring: luxury vinyl plank vs. tile vs. engineered wood. LVP handles a slab and moisture variance well and costs the least. Tile is durable in a bathroom but cold underfoot. Engineered wood looks best and costs the most, and it needs a stable subfloor.
- Windows and exterior door. This is where quality shows up on your energy bill. We fit Andersen and Pella units where the opening allows, and impact-rated glass matters in North Texas hail country.
- HVAC: ducted or ductless. Tying into the house system is cheapest if the garage is close to the main unit. A ductless mini-split costs more up front but gives the ADU its own control, which matters if you’ll rent it.
- Exterior: keep or replace the garage door opening. Most homeowners frame in the old door with a wall, window, and standard entry door. Keeping a roll-up for storage defeats the purpose.
What Garage Conversion ADU work costs in Carrollton, TX

Expect $45,000 – $130,000 for a Garage Conversion ADU in Carrollton. The low end is a simple studio with a half bath and no kitchen. The high end is a full one-bedroom with a complete bath, kitchenette, separate HVAC, and upgraded finishes.
| Line item | Typical range |
|---|---|
| Garage conversion, basic studio (no plumbing) | $30,000 – $55,000 |
| Conversion with half bath and kitchenette | $55,000 – $90,000 |
| Full one-bedroom with bath, kitchen, separate HVAC | $90,000 – $130,000 |
| Bathroom addition within the conversion | $9,000 – $28,000 |
| Window and door upgrades | $4,500 – $15,000 |
Four things push a job toward the high end: size, whether you add plumbing and a kitchen, the condition of the existing slab and structure, and finish grade. A garage with a cracked or settling slab costs more before finishes even start, and relocating a drain line means breaking and patching concrete. A written line-item estimate from us spells out demo, framing, mechanicals, finishes, and permits so nothing shows up later as a surprise. What it won’t include is furniture, appliances you supply yourself, or landscaping around the new entry unless you ask for it.
See the difference
Before
After
Before
After
Before
AfterWhat Carrollton’s older homes do to this job
Carrollton’s postwar building boom from the 1950s through the 1970s left large tracts of ranch homes that are now getting their first major remodels, and a garage conversion on one of these is different from converting a newer build. The original cast-iron drain lines under 1960s Carrollton ranch homes are failing across the board, and if your garage has a floor drain tied into that line, we plan for a repipe before the bathroom goes in. Carrollton’s codes are also stricter than neighboring Plano or Farmers Branch on alley access and drainage, which matters here because dumpster placement and concrete delivery in the older neighborhoods with rear alleys need staging planned before demo day, not after. Add North Texas expansive clay soils and a shallow slab that has likely moved, and slab condition and grading become real line items. It’s not an obstacle; it’s just what a Carrollton garage conversion actually involves, and we plan for it from the first walk-through. Homeowners often pair the new ADU entrance with Concrete Driveways & Concrete Work in Carrollton to give renters their own approach.

Serving Carrollton, TX – Our Local Coverage Area
We serve Carrollton and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked: Garage Conversion ADU in Carrollton

A Garage Conversion ADU in Carrollton typically takes 3 to 5 months from demo to final inspection. The permit review and the finish-selection timeline are the two things most likely to stretch it. Call (844) 560-0925 for a schedule based on your specific garage.
Yes. A Garage Conversion ADU in Carrollton requires building, electrical, plumbing, and mechanical permits, plus the inspections that make the space legal living area. Converting without permits creates a real problem when you sell. We pull the permits and manage the inspections for you.
Yes, a Garage Conversion ADU can be finished as a studio or office with no plumbing and minimal structural change. The trade-off is that it won’t function as a rentable or fully independent unit. Adding even a half bath is the most common middle path, and it keeps the plumbing work contained.
Most Garage Conversion ADU projects in Carrollton land between $45,000 and $130,000. The range tracks size, whether you add a bath and kitchen, and slab condition. Call (844) 560-0925 for an exact written quote; the estimate is free.
Every Garage Conversion ADU we build is covered by our 730-Day Done Right Promise: if it isn’t done right, we make it right, for two full years after completion. Our technicians have up to 12 years of experience, and the work is backed in writing.
Get a real number on your Carrollton garage conversion
A free on-site estimate for your Garage Conversion ADU in Carrollton starts with us walking the garage, checking the slab and any existing plumbing, and talking through whether you want a studio or a full unit. You’ll get a written, line-item quote with no surprises and a clear schedule. We answer the phone with a live person, 24/7. Call (844) 560-0925 to book yours.