Garage Conversion ADU in Farmers Branch: What It Actually Takes
A garage conversion ADU in Farmers Branch typically runs $45,000 to $130,000 and takes 10 to 16 weeks from permit to final inspection, depending on whether you’re keeping the existing slab and walls or building new MEP runs. The work turns an attached or detached garage into a permitted living unit with its own kitchenette, full bath, sleeping area, and separate entrance. Call (844) 560-0925 and we’ll schedule a free on-site estimate and walk the actual space with you.

From Empty Garage to Permitted Unit: How the Work Runs

Every garage conversion ADU we build in Farmers Branch follows the same five-stage sequence. Timelines shift with permit turnaround and how much of the existing structure stays, but the order doesn’t.
Stage 1: Assessment and layout (days 1 – 3)
We measure the slab, check ceiling height, and trace where the garage shares walls with the house. You decide the unit’s footprint right here: full studio, one bedroom, or one bedroom plus a kitchenette. That decision drives everything downstream, so it’s the first thing we lock.
Stage 2: Design and permit submission (weeks 1 – 3)
We produce the layout drawings, electrical and plumbing plans, and submit to the City of Farmers Branch for review. Plan review typically takes 2 to 4 weeks. You sign off on finish selections before we submit, so the permit package matches what actually gets built.
Stage 3: Demolition and rough-in (weeks 3 – 6)
The garage door gets removed and framed in for the new exterior wall and entry door. We cut the slab for plumbing if the bath isn’t landing over an existing drain, run new electrical circuits to a subpanel, and frame any interior partitions. Rough inspections for framing, electrical, plumbing, and mechanical all happen in this window. If the original slab was poured for a car and not a living space, this is where the floor build-up happens: a moisture barrier, insulation, and a new subfloor on top.
Stage 4: Insulation, drywall, and systems (weeks 6 – 11)
Spray foam or batt insulation at the walls and ceiling, then drywall, tape, and texture. HVAC gets set, the mini-split or ducted system goes in, and the full bath gets tiled and fitted. Kitchenette cabinets and countertops install in the back half of this stage.
Stage 5: Finishes, final inspection, and handoff (weeks 11 – 16)
Flooring, paint, trim, fixtures, and the exterior door and siding to match the house. Final inspection closes the permit. A garage conversion ADU here is a permitted dwelling, so the inspection has to pass before anyone lives in it. The whole job is covered by our 730-Day Done Right Promise, which means if something isn’t right, we come back and fix it.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
Choices That Shape the Unit: What You’re Actually Picking Between
The finishes and systems you choose move the number more than raw square footage does. Here’s what we walk Farmers Branch homeowners through, and the honest trade-off on each.
- Slab-on-grade vs. raised subfloor: Keeping the existing slab is cheapest, but a garage slab isn’t insulated and can wick moisture from North Texas clay. A raised subfloor with a vapor barrier and rigid insulation adds cost but gives a warmer floor and a better moisture barrier. Worth it if you’ll rent the unit.
- Mini-split vs. extended ductwork: A ductless mini-split is a clean, efficient install and avoids tying into an older central system that may be sized only for the main house. Extending ductwork works if the existing HVAC has capacity to spare. On 1950s-60s homes in ZIP 75234, spare capacity is rare.
- Kitchenette scope: A sink, two-burner cooktop, and undercounter fridge keeps the electrical load low. A full range and oven means a heavier circuit and more ventilation. Most Farmers Branch garage conversion ADUs land on the kitchenette side unless the tenant is family.
- Bath configuration: A walk-in shower is simpler to build and easier to maintain than a tub-shower combo, and it frees up floor space. If the unit will house an older relative, a curbless shower is worth the extra cost.
- Exterior door and window package: This is where buyers get real value. Therma-Tru entry doors and ES Windows or ECO Window Systems units give you a proper sealed envelope that holds up to hail season and cuts heat gain in a west-facing unit.
What a Garage Conversion ADU Costs in Farmers Branch, TX
Budget $45,000 to $130,000 for a permitted garage conversion ADU in Farmers Branch. Where you land inside that range depends on four things.

- Size and configuration: A 400 sq ft studio with a kitchenette sits near the bottom; a 600+ sq ft one-bedroom with a full kitchen pushes toward the top.
- Plumbing location: If the new bath sets near an existing drain line in the main house, you save. Cutting a new slab for plumbing and running to a distant stack adds cost.
- Electrical: A subpanel upgrade, new circuits, and a mini-split add up. Older homes here often need the service panel brought up to current capacity, which is real money.
- Existing condition: Original slab, settling, or old framing that needs correction all get handled before finishes go on.
A written estimate from us is line-itemed: demo, framing, MEP rough-in, insulation, drywall, finishes, fixtures, permit fees, and inspection costs are each spelled out. What’s typically not included is furniture, appliances beyond what you approve, landscaping, and any separate detached structure. Upfront pricing means the number you see is the number you pay, with no change orders unless you change the scope in writing.
See the difference
Before
After
Before
After
Before
AfterWhy Farmers Branch Lots Change This Job
Farmers Branch is essentially built out. Most of the work here happens inside established post-war ranch subdivisions, not on fresh lots, and that shapes a garage conversion ADU in ways it wouldn’t in a newer suburb. The original garages on 1950s and 60s homes are shallow and often set tight against a neighboring lot line, so the framing has to respect the existing setback before we ever move a wall. On the older streets, the small ranches are being replaced or expanded and two-story infills are squeezed onto the same lot, which means you may be converting a garage while the neighbor next door is running a demo. That’s a staging and protection problem the crew has to plan around. Inside the loop, the City of Farmers Branch permitting and inspection process moves exactly and expects the drawings to match the build. The older electrical and plumbing in 1950s and 60s homes almost always needs a closer look before conversion plans are final. And black-clay soil here swells and shrinks with the wet-dry cycle, so we check the slab for movement before building on top of it. This is also why homeowners often pair a conversion with drainage correction, or with Concrete Driveways & Concrete Work in Farmers Branch when the old apron needs fixing first. If you’re also reworking the wider property, our Home Additions & ADU in Farmers Branch page covers the bigger picture, and you can see all of it under our Home Additions & ADU service.
Serving Farmers Branch, TX – Our Local Coverage Area
We serve Farmers Branch and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked: Garage Conversion ADU in Farmers Branch

Plan for 10 to 16 weeks from the day permits are submitted to the day we hand you the keys. Permit review alone takes 2 to 4 weeks, and the build runs 8 to 12 weeks after that depending on scope and inspection scheduling. Call (844) 560-0925 for a timeline matched to your specific garage.
Yes. A garage conversion ADU is a permitted dwelling here and requires plan review, rough inspections, and a final inspection before anyone can move in. We prepare the drawings and pull the permits so the paperwork matches the build. Call us and we’ll walk through the permit scope on your property.
Sometimes. If the new bath sets near an existing drain and the framing stays intact, the job gets simpler and cheaper. Most garages here need at least a slab cut for plumbing and a framed-in wall where the garage door was. We confirm which side of that line you’re on during the free on-site estimate.
Yes, usually by a wide margin. A garage conversion ADU in Farmers Branch runs $45,000 to $130,000, while a new detached ADU costs $90,000 to $220,000. You’re reusing the slab, exterior walls, and roof, which is most of the shell cost. Call (844) 560-0925 for a firm number on your garage.
The 730-Day Done Right Promise covers the workmanship on your garage conversion ADU. If something isn’t right, we come back and make it right. It’s one of the longest workmanship guarantees you’ll find on residential construction. Call for the details in writing before you sign anything.
Get a Free Estimate on Your Garage Conversion ADU
We’ll come out to your Farmers Branch property, measure the garage, and give you a line-itemed estimate with no obligation. On the call we confirm your timeline, walk through the permit process, and answer your finish questions. If you’re also considering a new driveway or resurfacing while the crew is on site, homeowners often pair this with Asphalt Driveways & Resurfacing in Farmers Branch. Reach us at (844) 560-0925, and see our Farmers Branch service area for how we cover the city.