What a Garage Conversion ADU in Garland actually involves
A Garage Conversion ADU in Garland turns an existing attached or detached garage into a legal, rentable living space, and most projects here run $45,000 to $130,000 from demo to final inspection. A simple studio with a kitchenette and a 3/4 bath takes about 10 to 14 weeks; a full one-bedroom with a relocated laundry and a dedicated meter can stretch to 5 or 6 months. The number and the schedule both hinge on what’s under the slab and how much plumbing and electrical you’re moving. Call (844) 560-0925 and we’ll walk your garage, check the foundation, and give you a written line-item estimate.

How we take a Garland garage from storage to a permitted unit

Every conversion moves through the same sequence, and the order matters because Garland’s inspections happen in stages. Here’s what actually happens week by week.
Stage 1: Assessment and permit drawings (weeks 1 – 3)
We start by measuring the slab, checking for the cracks and settlement that older Garland garages tend to carry, and confirming the ceiling height and framing. You’ll decide the layout, whether the unit is a studio or has a separate bedroom, and whether the garage door gets removed and framed in or stays as a decorative facade. From there an architect or designer drafts the permit set. Garland requires a site plan, floor plan, and energy compliance documentation before a permit is issued. This is the slowest stage because the city review clock is out of our hands, so getting the drawings right the first time saves weeks.
Stage 2: Demo and rough-in (weeks 3 – 5)
Day one of construction is demo: the overhead door and tracks come out, and any old shelving, water heater platform, or gas stub goes with it. Then the rough-in begins. Framing goes up for the new walls, plumbing lines are run for the kitchenette and bath, and electrical is pulled for outlets, lighting, and the panel upgrade your unit will need. If the slab has to be cut for a new drain line, that’s a decision point: cutting the slab adds cost and dust, while running a raised floor over it eats ceiling height. We show you both before anyone picks up a saw. Rough trades get inspected before anything is closed up.
Stage 3: Insulation, drywall, and systems (weeks 5 – 9)
Insulation and drywall close up the walls, then the finish trades come in. A mini-split goes in for heating and cooling, sized to the square footage of the unit, since Garland summers push a garage-turned-apartment harder than the main house. The bath gets tiled, the kitchenette gets set, and flooring goes down. You’ll pick your finishes around this stage: cabinet fronts, countertop, tile, and paint. That’s also when we set the appliances and connect the water heater.
Stage 4: Final inspections and finish-out (weeks 9 – 12)
Final inspections cover building, electrical, plumbing, and mechanical, and a Garland permit isn’t closed until all four sign off. We schedule those in the order the city wants them and handle the paperwork. Then it’s the punch list: trim touch-ups, a final clean, and a walkthrough with you. Anything that doesn’t hold up in the first two years is covered under the 730-Day Done Right Promise, which is one of the longest workmanship guarantees in residential construction.
Stage 5: Occupancy and the finish line (week 12+)
Once the certificate of occupancy is issued, your unit is ready for a family member or a tenant. We hand over the as-built drawings and inspection records. If you’re planning to rent it, that documentation matters for your records and for any future refinance or resale.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The options you’ll choose between
Most of the cost and feel of a Garland Garage Conversion ADU comes down to a handful of spec decisions. Here’s what we walk you through.
- Slab cut vs. raised floor. Cutting the existing slab for a new drain keeps ceiling height and looks cleanest, but adds $2,000 to $4,000 and dust. A raised, insulated floor keeps the slab intact but eats 6 to 10 inches of headroom, which matters in a 1950s Garland garage that was never tall.
- Prefab modular shell vs. stick-built inside the garage. A modular unit like those from Boxabl or Cover can be dropped and set, and it shaves weeks off the build. Stick-built lets you use every inch of the garage and match the house. For most Garland garages, stick-built fits the existing footprint better and lets you tie into the main house’s plumbing.
- Mini-split vs. ducted system. A ductless mini-split is cheaper to install and efficient for a unit under 600 square feet. If your main house HVAC is near the end of its life, extending ductwork might make sense and gives you one system to service.
- Galley kitchenette vs. full kitchen. A kitchenette (sink, two-burner cooktop, small fridge) keeps cost and plumbing runs down. A full kitchen with a range and full-size fridge adds $8,000 to $15,000 but makes the unit rentable as a standalone apartment.
- Detached meter vs. shared utilities. A separate electrical meter and water tap make the unit a true ADU and easier to rent, but each tap adds to the bill. Sharing the main house utility is cheaper and simpler if the unit is for family.
What a Garage Conversion ADU costs in Garland, TX
For a garage conversion in Garland, plan on $45,000 to $130,000 depending on size, how much plumbing and electrical you relocate, and finish level. That range reflects the full job: design, permits, foundation work, framing, mechanical, and finishes.
The variables that push a job toward the low or high end:

- Square footage. A 300-square-foot single-car garage lands near the bottom. A 600-square-foot double garage with a bedroom jumps to the middle and up.
- Foundation condition. Garland sits on expansive black-clay soil, and older slab-on-grade garages often have cracks or settlement. Leveling and re-piering before construction can add several thousand dollars, but skipping it means cracks in your new walls.
- Plumbing and electrical relocation. Keeping the kitchen and bath close to existing supply lines saves money. A bath across the garage from the main stack adds pinhole and drain runs that cost more.
- Panel capacity. Older Garland homes often have a 100-amp panel that won’t carry a new unit’s load. A service upgrade adds cost.
- Finish grade. Luxury vinyl plank and a prefab shower keep the number down. Tile throughout and custom cabinetry push it up.
A written estimate from us is line-item, so you see every material and every labor line. What it doesn’t usually include: landscaping, connecting to the main house furnace if you go that way, and anything discovered behind the drywall after demo. We tell you when those come up before we touch them, which is what “upfront pricing, no surprises” means in practice. Ask about the $1,000 off on projects over $10,000 and 0% financing for 18 months while you’re on the call.
See the difference
Before
After
Before
After
Before
AfterWhat Garland homes specifically do to a garage conversion
Garland’s housing stock went up in one build-out from the 1950s through the 1970s, so almost every garage you’ll convert here is a postwar ranch or brick-veneer tract house. That single-era stock changes the job. Ceilings are lower than modern builds, which is why we check headroom before promising a layout. Many garages have a step-down slab, so we frame a small landing rather than fight the grade. Pier-and-beam garages need new piers before the unit carries a full bath and kitchen weight, and slab garages frequently show the movement that North Texas black-clay soils cause as they swell and shrink through the wet-dry cycle.
The permitting side is its own reality. Garland’s older platting and permit history sometimes means the city has to verify what was originally approved before it will sign off a new occupancy for a garage. Homes in the 75040 and 75041 ZIP codes, in established neighborhoods off Garland Road and in the areas near downtown Garland, tend to have the most complete records because those houses have been through remodels before. Newer areas further out, around the 75042 boundary, are more consistent. We pull the permits and handle the inspections, which matters when the city wants a full record of the conversion. This is a remodel-and-rehab market, not a new-build one, and the garage work here reflects that: we’re working with what a 1962 ranch gave us, not starting from open ground.
Serving Garland, TX – Our Local Coverage Area
We serve Garland and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked – Garage Conversion ADU in Garland

A simple studio conversion takes about 10 to 14 weeks, and a one-bedroom with a full kitchen runs 5 to 6 months. The permit review in Garland is the biggest variable, since the city’s plan check can add several weeks depending on the queue. Call (844) 560-0925 for a real schedule based on your garage.
Yes, a Garage Conversion ADU in Garland always requires a building permit and inspections for electrical, plumbing, and mechanical, and the unit needs a certificate of occupancy before it can legally be lived in or rented. The city won’t sign off without the full permit set. We pull the permits and manage every inspection so you aren’t chasing the city yourself.
Often, yes. If your garage already sits near the main house’s plumbing stack and the slab is sound, a studio layout can use the existing supply and drain lines with minimal cutting. The foundation is the one thing we check before we promise anything: if the slab has substantial cracks or the pier-and-beam is sagging, that gets handled first. Call (844) 560-0925 and we’ll tell you which case yours falls into.
Most Garland projects land between $45,000 and $130,000. The low end is a smaller single-car garage with a kitchenette and a shared utility; the high end is a double garage with a full kitchen, a bedroom, and a detached meter. We give you a written, line-item estimate before any work starts so you know what each piece costs.
Every conversion is backed by the 730-Day Done Right Promise, which covers workmanship for two full years. If something isn’t right, we come back and make it right. Our technicians have up to 12 years of experience, and every crew member is background-checked and arrives in uniform.
Ready to price your Garland Garage Conversion ADU?
Call (844) 560-0925 to schedule a free on-site estimate for your Garage Conversion ADU in Garland. We’ll walk the garage, check the slab, talk through the layout you have in mind, and leave you with a written line-item estimate and a realistic timeline. We also cover Garland and the surrounding areas, and if your project grows into more, see our Home Additions & ADU service or the wider Home Additions & ADU in Garland page. Many homeowners also pair a conversion with a new Concrete Driveways & Concrete Work in Garland project or Asphalt Driveways & Resurfacing in Garland to open up the parking the garage used to provide.