New Detached ADU in Allen: What It Takes and What It Costs
A new detached ADU in Allen typically runs $45,000 – $130,000 and takes four to seven months from the first site walk to final inspection, depending on size, finishes, and how much utility trenching the lot demands. You’re building a second, fully independent structure on your property: its own slab, its own roof, its own electrical service and plumbing stub, its own address. Call (844) 560-0925 to set up a free on-site estimate and get a written line-item scope before you commit to anything.

How the Build Actually Runs, Stage by Stage

Detached means detached, and that changes the whole sequence. Nothing shares a wall with your house, so no temporary shoring, no tying into the existing roof line, and no working around your family’s daily routine once the shell is up. Here’s what the calendar looks like.
Stage 1: Site walk and feasibility (week one)
We walk the lot with you and map setbacks, easements, the alley or side-yard access for equipment, and where utilities enter the main house. This is the stage where you decide the footprint (a one-bedroom around 500 – 650 square feet or a two-bedroom closer to 800 – 1,000), whether it’s a slab-on-grade build or something else, and roughly where the front door faces. On Allen lots you also want to know your plat restrictions and any HOA architectural rules before we draw anything, because those two things can reshape a plan faster than budget can.
Stage 2: Design, engineering, and permitting (weeks 2 – 10)
Plans get drawn, and in North Texas a structural engineer stamps the foundation design because of the clay. That stamped drawing then goes to the City of Allen for building, electrical, plumbing, and mechanical permits plus zoning review. Permit timelines vary by workload at the city, and this is usually the longest quiet stretch of the project. You’ll be making finish decisions here while you wait: exterior cladding, roof material, window package, flooring, and whether the unit gets its own meter.
Stage 3: Site prep and foundation (weeks 2 – 4 of construction)
The crew clears and grades, sets forms, and installs the under-slab plumbing before the pour. We call for the foundation inspection and pour once it passes. For a detached unit, trenching for water, sewer, and electrical runs from the house or the meter to the new structure. That trench length is a real line item, and lots with a long setback or a rear utility easement pay more for it.
Stage 4: Shell, rough-in, and inspections (weeks 5 – 14)
Framing goes up, then the roof, then windows and exterior doors so the building goes dry. Electrical, plumbing, and HVAC rough-in follow, and each trade gets its own inspection before insulation. Insulation and drywall come next, then the finish trades: flooring, cabinets, countertops, fixtures, trim, paint.
Stage 5: Finish, final inspection, and handoff (weeks 15 – 22)
Final touches, exterior grading and drainage correction, and the city’s final inspection. You walk the unit with us, we build a punch list, and we close it out. Every ADU we build carries the 730-Day Done Right Promise, so if something isn’t right after you move in, we come back and make it right.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Decisions You’ll Actually Make
Most of the money in a detached ADU is decided in three conversations: how big, how it’s built, and how it’s finished. Here’s what you’re really choosing between.
- Size and layout. A one-bedroom studio-style unit keeps cost near the bottom of the range. A true two-bedroom with a full kitchen pushes toward the top. Every additional 100 square feet adds cost in foundation, framing, roofing, and finishes at once.
- Foundation and structure. Slab-on-grade is standard here and the most economical. Engineered pier-and-beam designs cost more up front but can make sense on lots with known soil movement. Talk to your engineer about what your lot’s soil report says before you pick.
- Roof. Architectural composition shingle is the value pick and handles Texas hail about as well as anything at its price. Standing-seam metal costs more but you’ll likely get a longer service life and better hail performance. Either way, use rated underlayment.
- Windows and doors. Low-E, impact-rated glass matters in Collin County hail country. We work with brands like ES Windows and Therma-Tru, and the trade-off is straightforward: better glass costs more now and saves on energy and storm damage later.
- Exterior cladding. Brick veneer to match your house, fiber cement siding, or stucco. Brick and fiber cement hold up well in North Texas heat and sun. Match the main house if resale value matters to you.
- Utilities. A separate meter means the tenant pays their own bills, which is the better long-term setup for a rental. Tying into the main house service is often cheaper to install but complicates billing and code compliance.
What a New Detached ADU Costs in Allen, TX
Plan on $45,000 – $130,000. That range covers a compact one-bedroom build up to a fully finished two-bedroom unit with its own metered service. Here’s what moves you up or down inside it:
- Square footage: the single biggest variable. Every 100 square feet adds real money across every trade.
- Utility run distance: the farther the unit sits from the house or meter, the more trenching, pipe, and wire you pay for.
- Finish grade: builder-grade laminate and stock cabinets sit at the low end. Custom cabinetry, stone counters, and tile throughout push toward the high end.
- Site conditions: a flat, open lot is cheaper to build on than one that needs grading, retaining, or drainage correction.
- Permit scope: a unit with its own electrical service and separate address adds permit and inspection cost over a simple tie-in.
A written estimate from us lists line items by trade, so you can see exactly where the number comes from. What’s usually not included: landscaping restoration beyond basic grading, fencing around the new unit, and any furniture or appliance package you choose to add. If your project is part of a full Home Additions & ADU in Allen scope that touches the main house too, we’ll price both on the same document so the numbers are easy to compare.

See the difference
Before
After
Before
After
Before
AfterWhy Allen Lots Change This Build
Allen’s housing stock mostly dates from the 1990s through the 2010s, which means most lots we build on were graded and developed in that same window. That matters for a detached ADU in two ways. First, the black clay under nearly every slab here swells and shrinks hard with the wet-dry cycle, so a foundation on a new detached structure needs an engineered design rather than a generic one. A home that looks fine in wet spring weather can show movement by late summer, and a new ADU foundation is no exception. Second, mature subdivision lots mean tight side-yard access and established trees with root zones that restrict where equipment can go. We plan equipment routes and staging on the site walk so we don’t tear up a lawn or clip a fence panel getting a skid steer to the back corner.
Many Allen subdivisions carry HOA architectural review requirements alongside city permitting, and the two run on separate clocks. Getting drawings approved by the HOA early usually saves weeks on the back end. If the lot is in 75013 or 75002, we’ll confirm which jurisdiction and which review boards apply.
Serving Allen, TX – Our Local Coverage Area
We serve Allen and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked: New Detached ADU in Allen

Four to seven months from site walk to final inspection is typical. Permitting and design usually eat six to ten weeks of that. Call (844) 560-0925 for a realistic timeline once we’ve seen your lot.
Yes. A new detached ADU needs building, electrical, plumbing, and mechanical permits from the City of Allen plus zoning review, and in most subdivisions HOA architectural approval as well. We pull the permits and coordinate the inspections, so you’re not chasing the city yourself.
That’s the advantage of detached. The main house stays untouched except where we tie in utilities, so there’s no temporary wall, no shoring, and no dust in your living room. The only main-house work is the utility connection point.
Expect $45,000 – $130,000 depending on size, finish level, and how far utilities have to run. Call (844) 560-0925 for an exact quote. Estimates are free and written line by line.
Every ADU we build is covered by the 730-Day Done Right Promise. If something isn’t right, we make it right. That applies to our workmanship, and manufacturer warranties cover the materials on top of it.
Get a Free Estimate on Your New Detached ADU
Call (844) 560-0925 and we’ll schedule a free on-site estimate at your Allen property. We’ll walk the lot, talk through size and layout, and hand you a written line-item scope within a few days. Calls are answered by a live person 24/7, and the price we quote upfront is the price you pay. Homeowners often pair this work with Concrete Driveways & Concrete Work in Allen or Paver Driveways in Allen once the unit changes how the property is used.